Tepco Warns of Delay in Fukushima Plant Shutdown
Tokyo Electric Power Co. said Wednesday it may fail to achieve "cold shutdown" at the Fukushima Daiichi nuclear plant in January, as the world's worst nuclear crisis in 25 years rumbles on.
Efforts to decontaminate highly radioactive water at the earthquake-hit facility have been delayed by repeated breakdowns of cesium absorption instruments, which have caused water leakage and malfunctioning of pumps, threatening to delay the process of stabilizing the stricken plant.
"It's possible that decontamination may not be completed as planned by the year-end, although we have not yet decided to change the target. That could affect the cold shutdown process," a company spokesman told Reuters.
His comments follow a similar statement Tuesday, reported in the Nikkei business daily, from Junichi Matsumoto, a Tepco spokesperson on nuclear issues.
Cold shutdown is usually defined as meaning the water in a reactor is below 100 Centigrade at normal atmospheric pressure, making its radioactive fuel safe from heating up again.
Tepco also confirmed Wednesday that it is testing a new radioactive water processing instrument as it struggles to cope with the damage wreaked by the magnitude 9.0 earthquake and tsunami that devastated Japan's northeast coast March 11.
With only an estimated 42,000 tons of highly contaminated water having been processed by Aug. 9, roughly 120,000 tons are still left in the basement in turbine buildings and elsewhere.
Tepco had set a goal of processing 200,000 tons of radioactive water by year-end since more water will be contaminated in the process of bringing the damaged reactors under control.
Tepco officials and nuclear crisis minister Goshi Hosono plan a joint news conference Wednesday to explain progress on work to bring the damaged reactors under control.
The test run of Toshiba Corp.'s cesium adsorption instrument, known as Sarry, is being carried out by running water with low-level radiation through equipment from French nuclear firm Areva SA and U.S. nuclear waste management company Kurion Inc. It is scheduled to start operating fully as early as Thursday, Tepco officials said.
Sarry is relatively easy to maintain because it has fewer pumps, the breakdown of which have been a major reason for delays. Even if the system's overall operating rate holds steady at 90 percent, roughly 195,000 tonnes will be processed this year.
(Reporting by Tetsushi Kajimoto; Editing by Alex Richardson)